16 Springvale St · Thrive One Trust Data as at 24 Sep 2026 · PLANS 29 Jul · DECKING PLAN v2 24 Sep

Site plan

The block, the house, the north corner — and where every work package sits.

1. The block in six zones

One picture the four of us can point at. Each zone has its packages on the Workfronts board and its clocks on Compliance; the drawings behind it are on Drawings & files. This page is the first version of the integrated site plan Marcos and Claude maintain under D45.

Schematic site plan of 16 Springvale St, not to scale, six zones numbered 1 to 6 Boothby Park rear · north-east N rear boundary (diagonal) 6 Backyard & landscaping 5 lawn 4 North corner pool · deck · utilities wedge 16.30 m² Pool kidney-shaped, in-ground 2.8 × 7.52 m new or existing? Deck 86.55 m² deck — side of house proposed frameless glass fence 15.53 lm pool pump alfresco 2 House interior dwelling 143.37 m² living · kitchen · 3 bed bath · ensuite · laundry 3 Roof & solar tile roof 20° · truss D41 solar panels off 29 Sep fire-rated wall Granny flat converted garage 53.88 m² porch sewer pump (granny flat) trench (sewer line) 1 Front yard & carpark meter box Springvale St front · south-west · 12 m frontage
Schematic — not to scale. Dimensions from Rei's PLANS (29 Jul 2026, lot 806 m², 12 m frontage, ~40 m deep) and DECKING PLAN v2 (24 Sep 2026).

Legend

Symbols: dashed blue line = proposed glass fence · orange hatch = the 2.8 × 7.52 m section drawn separately on DECKING PLAN v2 · grey hatch = the 16.30 m² wedge · dashed grey line = sewer trench · red bar = fire-rated wall · orange dot = granny-flat sewer pump.

2. Why the north corner is its own workfront

Four packages (P2, P9, P10, P11) share the strip between the back of the house and the rear boundary, and they can only happen in one order. It is the workfront with zero float to the definitive pool safety certificate on 16 Nov (critical path, WBS v2 · 21 Sep).

Sequence (WBS v2, F5)

  1. Granny-flat sewer pump — bought; installed and tested before any board goes down. Plumbing under the deck is done (23 Sep). to install
  2. Trench (sewer line) — Dean, W40 (28 Sep–2 Oct). Package P2.
  3. Deck substructure — posts, footings, stirrups, 75 mm clearance; one party responsible, RPEQ Form 15 + QBCC carpenter with HWI. Structure 12–23 Oct. quote conditions open
  4. Coping + pool surrounds — on Joana's drawing, 12–23 Oct, alongside the deck structure. Package P10.
  5. Pool interior resurfacing — 26 Oct–6 Nov (resurfacing co. 2 is the only one that fits October; site visit Thu 25 Sep).
  6. Deck boards — 26 Oct–6 Nov, on the finished substructure.
  7. Frameless glass fence 15.53 lm + self-closing gate — 9–13 Nov; not yet quoted; removed glass panels not yet counted.
  8. Definitive PSC — Form 23 — Mon 16 Nov, then backyard landscaping 16 Nov–4 Dec (P11).

Who owns what

Constraints we hold to

Open geometry questions (for Rei)

3. Zones, packages, owners

Numbering and names are the WBS v2 (21 Sep) as Rei uses them: P0–P15. Roof restoration and the ducted AC sit outside the WBS numbering (— in the source). Allocations per package are on Cash; stage of each package on the board.

ZonePackagesOwnerComplianceStatus
1 · Front yard & carpark P12 Front yard + carpark + entry deck + front drainage (23 Nov–4 Dec) · P13 Granny flat — Hamilton milestones 5–9 (28 Sep–20 Nov) · deck 9B1 front (rebuild with clearance or replace with non-timber access) Rod (P12) · Rei (P13) Granny flat: BA via Apex, council search D24, HWI, Form 16s, Form 21 · smoke alarms D42 (CoTC, Form 24) Apex scope in writing Fri 26 Sep P12 after Joana
2 · House interior P1 Termite, timber & structure · P2 Plumbing · P3 Electrical (fit-off, alarms D42) · P4 Layout, fire-rated wall, doors/glass/flooring/kitchen · P5 Bathroom 1 · P6 Ensuite (Drew, D39) · P7 Bedrooms (built-ins) · P8 Painting in/out (Javier) · AC ducted (D9, outside the WBS) Rei (P1, P2, P4–P8) · Rod (P3, AC — Jean runs the AC quotes) Form 16 fire wall before plasterboard Fri 9 Oct · Form 4 per plumbing job · CoTC · AS 3740 waterproofing Form 16 · AS 3660 termite + reinspection · AS 1288 glass zero float 9 Oct interior 2 weeks float to PC 4 Dec
3 · Roof & solar Roof restoration + gutters (outside the WBS — done) · solar panel removal 29 Sep · P1 roof truss with fire damage near the chimney (D41) · P3 CoTC for the solar circuit Rei Form 15 + Form 16 on the truss · photos of the sealed solar penetrations · fireplace: decommission and declare, or divert the flue (D41) roof done truss in the engineer's visit by 2 Oct
4 · North corner P9 Decking — 9A living deck 94 m² as drawn (structure 12–23 Oct, boards 26 Oct–6 Nov) · P10 Pool — interior, coping, surrounds, barrier + PSC, filter moved off the wall (12 Oct–16 Nov) · P2 trench + sewer pump (W40) · P0 deck and pergola demolition (done) Rod (P10) · Rei (P9 structure) · Rod + Joana (drawing) PSC 8 Oct (Plan A) → Form 23 definitive 16 Nov · Form 15 deck substructure · like-for-like, no BA · HWI + QBCC on the deck zero float to 16 Nov Joana's drawing ~2 Oct
5 · Backyard & landscaping P11 Landscaping + fences — termite-affected fence sections, stumps, pruning, 75 mm clearance (16 Nov–4 Dec) · watch list, not in the EAC: patio cover, rear deck 9B2 (D35) Rod Bang report + AS 3660 reinspection · fencing invoice · rear deck 9B2 would need a BA after PSC fence +$4k proposed in v2, not budgeted
6 · Boundaries / Boothby Park P11 rear boundary fence (active termites, R19) · P15 Sales pack — title, plan and Form 2 · wedge 16.30 m² geometry against the diagonal boundary (P9) Rod (P11) · Marcos + Jean (P15) · Rei (wedge) Form 2 pack from the certificates folder · no structure over the boundary without a drawing wedge to confirm with Rei

4. What each zone still needs drawn

Under D45 we run the works by workfronts with partial drawings instead of full working drawings; these are the four drawing obligations that keep that safe. Latest drawings and where they live: Drawings & files.