Reference · Thrive Proptech Data as at 23 Sep 2026

Reno OS v1.3

The short rulebook: principles, the 9 gates and the 6-stage package card.

v1.0 5 Sep · v1.1 6 Sep (Approvals & Compliance) · v1.2 10 Sep (engaging trades; the Hamilton contract) · v1.3 23 Sep (six-stage package card, adopted at G5). Applies to 16 Springvale St and to the next buy-renovate-sell / buy-renovate-hold deals. How it is used day to day, with worked examples and a glossary, is on the Playbook.

1. Why it exists

Marcos's diagnosis (5 Sep): Thrive was executing service packages without an integrated design or an analytical structure. Reno OS is the minimum framework: nine sequential gates, each with an explicit kill criterion; a single package-approval rule (ARV ÷ cost ≥ 2.0×); an all-in cost nobody can leave out; and a compliance dossier built during the works, not at the end. In a renovation run with individual trades (no head contractor, no full working drawings) the unit of management is the work package — and v1.3 gives every package a card with an exit criterion per stage.

2. Standing principles

3. The nine gates

GateWhat must be readyDies if…
G0 MandateInside the buy box: ticket ≤ $1.1M; ≥ 400 m² for a renovation; Gold Coast, Brisbane bayside or Sunshine CoastOutside the buy box. Five minutes, no exception for "opportunity"
G1 Closed comps≥ 3 settled sales in the last 6 months, ≤ 1 km, same floor-area bandThe evidence is asking prices, not settlements
G2 Feasibility lockMaximum price calculated before any offer: GDV − reno with contingency − holding − exit − acquisition − target profit. The vendor's ask is information, never an anchorAsk above the maximum + 5%. This is where Springvale got away
G3 QLD due diligenceForm 2 before the offer (encumbrances, easements, covenants). B&P focused on termites. City Plan overlays (flood, bushfire, coastal, vegetation; Koala Priority Area in Redlands). Measured area, not the listing's. Title: owner-builder notes and Form 21 for all earlier worksMaterial encumbrance or area variance > 10%
G4 Capital and structureLoan agreements signed, SPV/Trust set up, Australian-resident trustees, irrevocable foreign-beneficiary exclusion clause in the Trust DeedClause missing → AFAD 8% + FIRB ≈ $80k that wipe out the margin
G5 Scope freezeEvery package with a ratio ≥ 2.0×. Contingency declared. Fixed quotes from QBCC-licensed trades before buying materials. Design package engaged and BA issued before any works that need one. Delivery regime in writing (never owner-builder)The approved total pushes the break-even above the defensible P50 — or the works proceed without a BA
G6 Works complianceEvidence collected during the works: Form 4 per notifiable plumbing job (10 business days); photos + AS 3740 certificate; Form 15/16 per wall removed; electrician's CoTC incl. interconnected photoelectric alarms (AS 3786, Form 24); QBCC licence per trade. BA if there is a secondary dwelling with a kitchenette. PSC after the deck and landscaping, within 90 days of settlementThe pool certificate lapses, or works under a BA finish without a Form 21 — the buyer's bank refuses, the insurer refuses, council may enforce
G7 Mid-works checkpointActual vs allocated, package by package. No package paid without the critical-line gate and the evidence for that aspect. Remediation, waterproofing and the pool are the three the buyer auditsVariation > 10% — it becomes a partners' decision, not the site manager's
G8 Exit strategyAgent chosen through the R1 window, not by a casual referral. Form 2 built with the solicitor ~2 months before listing, with the compliance dossier attached. Our own B&P before listing. Photos before Christmas. Gold Coast window: late Jan to Mar; Dec is dead; April is tiredGoing to market without a written reserve price, or without a complete Form 2 (rescission up to settlement)
G9 Offer decisionAccept, counter or convert to hold-and-rent against the G8 reserve. No offer in 6 weeks → automatic repricingHolding the price above the reserve while burning monthly holding costs

Where 16 Springvale St is today: between G5 (23 Sep) and G7 (23 Oct) — see 30 Days and Workfronts.

4. Package card — six stages (v1.3)

Applies to every package over $5k. Marcos's stage names, adopted at G5 on 23 Sep. The live board per package is on Workfronts.

StageWhat must exist to leaveWho signsMoney
1 · Strategy / design solutionScope written and measured (m², lm, levels); a drawing where there is an interface (deck × glass × coping); the list of approvals and evidence the package will generate (BA? Form 15? Form 4? CoTC?); the B&P lines R# it closes; the 2.0× ratio if discretionaryPackage owner + integratorPackage BZ confirmed; indicative EAC
2 · Quotes≥ 2 quotes on the same scope and drawing, in the name of ThriveCo One ATF Thrive One Trust, with ABN/QBCC when > $3,300, explicit inclusions and exclusions, payment milestones tied to physical delivery (never > 50% before the end)Package ownerPackage EAC = lowest reconciled quote
3 · Selection / contractOne-page comparison (price · scope · licence/HWI · payment · risk on the buyer's B&P) → approval authority G2 (> $5k or > 10% of the package = four partners) → written contract, variations in writingFour partners (or two, per the authority)Deposit only against a signed contract
4 · ExecutionThe contract's physical milestones followed on site; a dated photo per milestone; any new scope goes back to stage 1 (it is not resolved on site)Package ownerInterim milestones against photo + measurement
5 · QA / evidenceThe document the buyer will ask for: Form 4 / CoTC / Form 16 / AS 3740 / AS 3660 / AS 1288 / HWI + photos; filed in the Remediation/ folder by R#; quality walkthrough (the standard is the product benchmark, not "that'll do")Integrator + one partner who is not the ownerNothing is paid without the previous milestone's document (G4)
6 · Final paymentBalance released; actual cost posted to the ledger against the package BZ; R# line closed; lesson recorded in Reno OSIntegrator + treasury (single account)Δ = EAC − BZ with cause (scope · price · omitted · contingency)
No package skips a stageNew scope on site goes back to stage 1. A quote without a shared drawing does not count as a quote. A contract without a comparison does not pass the approval authority.
The 10% ruleNo contract above 10% of a package's allocation is signed between gates — it either goes to G5 or waits for the next checkpoint. Every quote is reconciled against the WBS before it becomes a contract.
The R# rule (D43)Every line of the B&P we received closes as remediated, replaced by the works or disclosed — always with evidence filed by R#. No line stays "we don't know". Matrix on Compliance.

Roles: the package owner runs the supplier and the site; the integrator (Marcos + Claude) keeps the board, the sequence between packages, the BZ × EAC ledger and the evidence dossier; the gate decides money and scope. Without a general design, the integrator makes sure the partial drawings talk to each other.

5. Buyer's finance-ready checklist (QLD)

What the buyer's solicitor and bank look for, in order of blocking power: Form 21 (all works under a BA) → complete Form 2 → Form 24 (smoke alarms) → Pool safety certificate / Form 36 → Form 4 (plumbing) + AS 3740 (waterproofing) + CoTC (electrical) + Form 15/16 (structural) in the dossier → QBCC regime (owner-builder notice if applicable) → B&P and termite certificate. Each line has an owner and a moment in the plan; whatever is not in the dossier becomes a price discount at the negotiating table. State of 16 Springvale St on Compliance.

Package → approval matrix (Gold Coast): structural walls = BA if structural · granny flat / secondary dwelling = BA always, DA if an overlay applies · deck = BA (exempt only < 10 m² and < 1.0 m; like-for-like restoration = accepted development) · patio cover = BA (exempt only < 10 m², < 5 m, < 2.4 m, outside setbacks) · new bedrooms = BA if an opening is created (window, ventilation, NCC ceiling height) · bathrooms = no BA if not structural (Form 4 + AS 3740 + photos) · roof = BA if > 20% of the area · pool = the fence needs approval · electrical / AC / solar = CoTC · landscaping = council if the crossover changes; wall > 1.0 m = BA · painting, flooring, non-structural kitchen, styling = free.

6. Agent windows R1–R4

7. Founding lessons

G2 — a flip's profit is made at purchase. If G2 fails, the other eight gates are damage control. On Springvale the maximum price was set by the vendor, not by the feasibility lock; the current break-even and the scenario ladder are on The Deal.

BA before the works (6 Sep). The works started before the building approval — the design and approvals package has to be engaged at G5, not discovered at G6. Every week without a written position from the certifier is a wall that may have to be reopened.

The Hamilton contract (10 Sep). A package was contracted at 6× its allocation, including a bathroom that did not exist in the budget, and started a month before the gate that should have approved it. When the works run ahead of the gate, the gate stops being a decision and becomes a rubber stamp. Hence the 10% rule and the reconciliation of every quote against the WBS before it becomes a contract.