Playbook

How we run this project: gates, work packages, decisions and one ledger — with G5 and D37 as worked examples.

The short rulebook behind this page is Reno OS v1.3; the company-level rules are in the Governance Charter. Terms in bold on this site are defined in the glossary below.

1. The operating model in one picture

Operating model: weekly gate, decisions, work packages through six stages, one ledger, Tbrain pages, with the four partners around it Reicompliance &drawings Rodnorthcorner Jeanon site &evidence Marcosintegrator& cash Weekly gate · Wed 6 pmG5 done 23 Sep · next G6 30 Sep Decisions D#five lines in the minutes, same day Work packages P0–P15 1 Solution2 Quotes3 Contract4 Execution5 QA & evidence6 Final payment One ledgerBZ · EAC · paid · committed Tbrain pagesNow · 30 Days · WorkfrontsCash · Compliance · Market back to the gate every week

2. The nine gates

A gate is a decision point with a written kill criterion. G0–G3 belong to the purchase; G4–G7 to the works; G8–G9 to the exit. Full criteria in Reno OS.

3. The package card — six stages

Every package over $5k has a card. The live board is on Workfronts; the rules per stage are in Reno OS. What matters here is the evidence that moves a card from one stage to the next.

  1. SolutionWritten, measured scope (m², lm, levels); a drawing where packages meet (deck × glass fence × coping); the approvals and evidence the package will produce; the B&P lines (R#) it closes. Leaves on: acceptance criteria written and the package's BZ confirmed.
  2. QuotesTwo or more quotes on the same scope and drawing, in the trustee's name (ThriveCo One Pty Ltd ATF Thrive One Trust), ABN and QBCC licence above $3,300, explicit inclusions and exclusions, payment milestones tied to physical delivery. Leaves on: the lowest reconciled quote becomes the package EAC.
  3. ContractOne-page comparison (price · scope · licence and HWI · payment terms · buyer's B&P risk) → approval authority G2 → written contract, variations in writing. Leaves on: signed contract; the deposit is paid only against it.
  4. ExecutionContract milestones followed on site; a dated photo per milestone; any new scope goes back to stage 1 — it is not resolved on site. Leaves on: the last physical milestone photographed and measured.
  5. QA & evidenceThe document the buyer will ask for — Form 16 / Form 4 / CoTC, AS 3740, HWI certificate — plus photos, filed under Remediation/ by R#; a quality walkthrough against the product benchmark. Leaves on: document filed and checked by the integrator plus one partner who is not the owner.
  6. Final paymentBalance released; actual cost posted to the ledger against the package BZ; R# lines closed; lesson recorded in Reno OS. Leaves on: reconciliation to the WBS and Δ = EAC − BZ explained by cause (scope · price · omitted · contingency).

4. Two worked examples

G5 — Wed 23 Sep, 6 pm

Weekly gate with Rod absent. The five-line minute for the Doc and the group is still to be posted by Marcos.

What came in
  • Call 1 by Fri 25 Sep, equalised to $120,553 per partner (Jean 15,553 · Rei 14,553 · Marcos 15,553 · Rod 28,053 = $73,712) plus a $20k reserve for AC and pool surrounds (Cash · 22 Sep).
  • Deck (P9): like-for-like restoration of the 94 m², no BA; the offer to start on 1 Oct against three quotes ($12.5k boards-only · $24k · $28,879 with structure).
  • Apex scope: what "granny flat only" covers and whether Rei's drawings are accepted — needed in writing.
  • PSC plan: statutory deadline Wed 8 Oct — Plan A (temporary fence + Form 23 now, second Form 23 on the glass fence 16 Nov) or Plan B (Form 26 → three months).
  • D45: no full working drawings; run the project by workfronts with safeguards.
What was decided
  • The six-stage package card adopted (Reno OS v1.3); every package over $5k gets one.
  • D45 ratified (Rod absent): Rei prepares the technical drawings the certifier asked for; Apex certifies the granny flat and resolves the fire-rated wall; Marcos and Claude integrate the partial drawings into one site plan. Four obligations remain — Apex's written minimum submission, RPEQ engineer single visit with Form 15, Joana's north-corner and façade drawing, council search D24.
  • Deck starts 1 Oct only if a written quote in the trustee's name + ABN/QBCC + one visitable reference + the structure signed off are in hand — otherwise it goes to the next gate.
  • Apex written scope by Fri 26 Sep; RPEQ engineer by 2 Oct; Form 16 for the fire-rated wall before the plasterboard closes on Fri 9 Oct.
  • Next gate G6 Wed 30 Sep; checkpoint G7 Fri 23 Oct.
What moved, and where
  • Cash · calls: Call 1 amounts per partner and the $20k reserve.
  • Workfronts · board: P9 deck held at stage 2 (Quotes) with its start conditions; P14 design & approvals re-scoped under D45.
  • Compliance · clocks: Apex 26 Sep · RPEQ 2 Oct · PSC 8 Oct · Form 16 9 Oct.
  • The Deal · bridge: D45 shown as a proposal — P14 from $29,183 to ~$14–17k (indicative), EAC v2 ≈ $362.9k with the B&P liabilities — not yet the current EAC (The Deal · 21 Sep).
  • Workfronts · decisions: D45 recorded; open question — the valuer treating the granny flat as unapproved work, which the Apex scope and the BA are meant to close.

D37 — one budget

Raised 17 Sep, protocol written 21 Sep, tabled at G5 on 23 Sep. Owners: JJ and Marcos.

The problem

Two budgets were in circulation: Rei's spreadsheet ($250k + 10%, projection $251,715 — Hamilton under by $15k, no design package, no fire-rated wall, but with a $15.6k patio cover and $10k ducted AC that the WBS did not have) and the financial model's EAC. Two numbers meant two conversations.

The decision
  • One frame. The approved budget is the BZ $270,000 (G4, 5 Sep); it only changes by a formal re-baseline by the four partners at a gate.
  • The projection is the EAC, dated (MRF-2026-09-21), updated at every quote, contract, paid milestone or gate.
  • Budget cover = BZ ÷ EAC is the weekly metric.
  • Rei's spreadsheet becomes the quotes and physical-execution tab — one source of truth, not two.
The number that moved

BZ $270,000 → EAC $356,084, budget cover 0.76× (The Deal · 21 Sep). The EAC was $336,084 on 17 Sep; the bridge explains every step by cause — Hamilton +36,545 · design & approvals +21,183 · pool +10,000 · fire wall +5,500 · already overspent +8,856 · contingency −16,000 · AC +15,000 · pool surrounds +5,000. Each $10k of reno moves the break-even by about $10.3k, or $2.5k per partner (The Deal · 21 Sep).

The page that changed

Cash now shows budget cover next to the bank balance, paid, committed and to-go; cost to complete is BZ | EAC | Δ | cause per package. The Deal owns the EAC and the bridge.

The routine that changed

Every Monday the bank statement is classified into the ledger by package, budget cover is recalculated, and any Δ gets a cause. Rei's spreadsheet feeds quotes in; it no longer carries a second total. Watch-list items (deck mid-quote, floor removal, rear deck, patio cover, solar, Joana) stay outside the EAC until they pass the 2.0× ratio at a gate.

5. Change management

Every change goes through a package card, a decision D#, a number that moves and a note in the minutes. That is the whole discipline.

How a change enters

  • Package card first. New scope goes back to stage 1 of its package — written, measured, with acceptance criteria — before anyone asks for a quote.
  • Decision D#. Money or scope is decided at the gate and numbered. Five lines: decided · who does what by when · number that moved · open question · next gate.
  • A number moves. The package EAC changes on the ledger with a cause (scope · price · omitted · contingency); budget cover follows.
  • A note in the minutes. Same day, in the Doc and in the partners' WhatsApp group.

Approval authority (G2)

  • Up to $1,000: any partner, notifying the group.
  • $1,000–5,000: two partners.
  • Over $5,000, or over 10% of a package: the four partners, at the gate.
  • A variation over 10% of a package's allocation between gates is a partners' decision — it goes to G5 or waits for the next checkpoint (G7, 23 Oct). Full rules on Cash.

What we do not do

  • Pay a trade without a quote in the trustee's name. A quote to a partner personally leaves the warranty and the Form 2 line orphaned at sale.
  • Start a package with no acceptance criteria written. "Looks good" is not a standard; the benchmark is.
  • Close a wall without the Form 16. The fire-rated wall inspection comes before the plasterboard on Fri 9 Oct — zero float. See Compliance.
  • Pay against an invoice's sequence. Milestones are released against a dated photo, the Form or CoTC and the reconciliation to the WBS — evidence before payment.
  • Sign a contract over 10% of a package between gates. Lesson from the Hamilton contract (10 Sep): when the works run ahead of the gate, the gate stops being a decision.
  • Decide in the group and leave it there. If it is not in the minutes with a D#, it did not happen for the platform.

6. Our learning curve

This is the four partners' largest combined investment in Australia: a business loan of about $990k and a $1.2M play targeting $1.8M. We are learning it together, in public, with a method.

Why the platform exists

To make everything auditable and replicable: the next deal should start from this playbook, not from memory. Tbrain is the shared memory (one owner page per number), WhatsApp is the conversation (fast, but not a record), and Drive is the file (quotes, contracts, Forms, photos). A decision lives in all three: made in the group, numbered on Tbrain, evidenced in Drive.

Why we write in English now

We work with certifiers, trades, agents, the accountant and the lender in English. Keeping the platform in Portuguese created a second vocabulary — "frentes", "alçada", "ficha" — that none of them share, and it slowed us down at every hand-off. One vocabulary for everyone: the terms on this site are the ones we use with Apex, Hamilton, Grow and the agents, defined in the glossary.

7. Glossary

Australian construction-management terms as we use them on this site. Forms are explained one by one on Forms.

Work package (P0–P15)
One deliverable with an owner, a budget line and a card: P0 demolition, P3 electrical, P8 painting, P9 deck, P10 pool, P13 granny flat (Hamilton), P14 design and approvals, P15 sale dossier, and so on.
Stage
Where a package card sits: 1 Solution → 2 Quotes → 3 Contract → 4 Execution → 5 QA & evidence → 6 Final payment. A card leaves a stage only on evidence; no package skips a stage.
Gate (G0–G9)
A decision point with a written kill criterion. G0–G3 cover the purchase, G4–G7 the works, G8–G9 the exit. The partners' weekly meeting (Wed 6 pm) is the gate in session.
Decision D#
A numbered decision recorded in five lines: what we decided, who does what by when, the number that moved, the open question, the next gate. Posted in the minutes and the group the same day.
Baseline budget (BZ)
The approved reno budget, $270,000 (15 packages $254k + $16k contingency), set at G4 on 5 Sep. Frozen; changes only by a formal re-baseline by the four partners at a gate.
EAC / MRF
Estimate at completion = paid + committed + estimated to go — the Most Recent Forecast, named by date (MRF-2026-09-21 = $356,084). Updated at every quote, contract, paid milestone or gate.
Budget cover
BZ ÷ EAC. Today 0.76× ($270,000 ÷ $356,084). Below 1.0× the approved budget does not cover the forecast; the gap is a partners' decision (re-baseline or cut).
Break-even sale price (all-in)
The sale price at which the four partners get their capital back: (acquisition + reno + holding + $12k fixed) ÷ 0.975. Owned by The Deal.
ARV (after-renovation value)
What the finished house should sell for, read from comparable sales. Stated as P50 of twin comps with no location premium, with premium, and P90. Owned by Market.
Comparable sales (comps)
Settled sales only — within six months, within 1 km, same floor-area band. A listing or an asking price is not a comp.
Holding costs
What the house costs per month while we own it: Pepper Money interest, Allianz insurance, rates, water, power, fees — about $6,594 a month. Owned by The Deal.
All-in
Complete cost: purchase + transfer duty + legal + buyer's agent + reno with contingency + holding + selling costs. Never compare ARV with "purchase + reno".
Approval authority
Who can commit money: ≤ $1k any partner (notify); $1–5k two partners; > $5k or > 10% of a package, all four at the gate. Governance rule G2.
Evidence
What proves a milestone happened: a dated photo, the Form or CoTC for that aspect, and the reconciliation to the WBS. It comes before payment, never after.
Open item
Something we still owe or are owed, with an owner and a date — a missing invoice, an unanswered question to a supplier, a Form not yet filed. Listed on Workfronts.
Blocker
An open item that stops a package moving to the next stage or a trade starting — for example no written position from Apex before the granny-flat plasterboard.
Zero float
No spare days between a task and the deadline it protects. Form 16 for the fire-rated wall before the plasterboard on Fri 9 Oct, and the PSC on Wed 8 Oct, are zero-float.
Critical path
The chain of dependent tasks that sets the finish date; a day lost on it is a day lost on practical completion. Three paths here: compliance, north corner, interior.
Practical completion (PC)
The works are finished and fit for use, apart from minor defects; target 4 Dec 2026. Followed by Form 21, pre-sale B&P, photos and listing.
Building approval (BA)
The approval a private certifier issues before works that need one — here the granny flat. Retrospective approval is slow and the certifier can order finished walls opened.
Private certifier
A licensed building certifier who issues the BA, inspects stages (Form 16) and the final (Form 21). Ours is Apex, engaged for the granny flat.
RPEQ engineer
A Registered Professional Engineer of Queensland; signs the Form 15 for structural elements — the fire-rated wall, the roof truss and the deck substructure — in a single site visit.
Form 15
Design/compliance certificate from an engineer or designer: the element as designed complies. See Forms.
Form 16
Inspection certificate: a certifier or competent person inspected the built element (framing, fire-rated wall, waterproofing). See Forms.
Form 21
Final inspection certificate that closes a BA. Without it the buyer's bank and insurer may refuse. See Forms.
Form 23
Pool safety certificate (PSC), issued by a licensed pool safety inspector; the deadline here is Wed 8 Oct. See Forms.
Form 26
Pool safety nonconformity notice — the inspector's list of what fails; buys three months to fix. Plan B for the PSC. See Forms.
Form 36
Notice of no pool safety certificate, given at sale; the buyer then has 90 days to obtain a Form 23. Ours started that clock. See Forms.
Form 2
Seller disclosure statement (Property Law Act 2023): title, plan, rates, zoning, pool certificate, owner-builder notice. Built with the solicitor two months before listing. See Forms.
Form 24
Transfer form with the smoke-alarm declaration: interconnected photoelectric alarms (AS 3786) declared at sale. See Forms.
Form 4
Plumbing notifiable work form the plumber lodges within 10 business days of each notifiable job. See Forms.
CoTC
Electrical certificate of testing and compliance, issued by the electrician for each job — including the AC and the smoke alarms.
Home Warranty Insurance (HWI)
The QBCC scheme that covers residential work over $3,300 for six years and six months. The certificate must be in the trustee's name, or it does not exist for the buyer.
QBCC licence
The Queensland Building and Construction Commission licence a trade or builder needs for residential work over $3,300. Verified on the regulator's site before the first payment.
Building & pest inspection (B&P)
The report a buyer commissions before settlement. Ours from March has 27 lines (R#); each closes as remediated, replaced by the works or disclosed. A pre-sale B&P is booked for 14–16 Dec.
Pool safety certificate (PSC)
The Form 23. Needed on sale and on the statutory deadline of Wed 8 Oct here; issued only when the barrier complies. Plan A and Plan B on Compliance.
Like-for-like
Restoring an existing structure to the same footprint and function — here the 94 m² deck. Accepted development, no BA; an extension or new footings would need one.
North corner
The pool, deck and utilities zone at the rear of the block: pool interior, coping, surrounds, deck, frameless glass fence, sewer pump and trench. Rod's workfront.
Individual trades
Running the works with separate licensed trades and no head contractor. It saves margin but makes us the integrator: sequencing, evidence and warranties sit with us.
Full working drawings
A complete set of construction drawings (~$7k quoted) that every trade builds from. Under D45 we chose not to commission them; Rei prepares the technical drawings the certifier asked for.
Loose scope
Running packages from partial drawings and written acceptance criteria rather than full working drawings. Works when the safeguards hold and criteria are written per package before quoting.